The work goes on ... | |
Once we had started by cutting out the turf with the basic route we desired, we had to then peg out the levels to decide how much dig and fill there would have to be | |
After this was completed our friend John brought in a mini-digger to help with the hard work and he very skillfully cut out to the depths we had marked with the pegs | |
We then had to move enormous amounts of spoil from one point to another, making an embankment at the far station area to accept some of the excess | |
Once this was completed we put in edging wood (4"x1") so this could contain the granite when it arrived | |
A first layer of 20mm granite was laid at about 2/3" depth and was levelled against the wood edges to leave an infill remaining of 2" | |
Sleepers 2"x3"were spread along the bed. The rail was bolted down with gash end bolts and we used large washers with a neoprene washer attached for better grip | |
The woodwork for the level crossings was fitted | |
Then the remaining granite was laid around the sleepers to level off with the tops of the wooden edging and the tops of the sleepers | |